Cyprium's Nifty Restart Hits Wet Commissioning Phase

By Siam Sukkhee Trading Co., Ltd — 2026-11-06 — Bing News — copper cathode

Cyprium Metals closed out September with something tangible: acid in the heap leach pads at Nifty. First time in nearly twenty years.

That matters because it's the point where you stop talking about commissioning and start producing actual copper, even if it's only trial volumes during the ramp-up phase.

The Western Australian complex has been in rebuild mode since Cyprium took the restart lead. Phase 1 targets around 6,000 tonnes of copper cathode per year, using the existing heap leach and solvent extraction equipment rather than building everything from scratch. That's the sensible play when you've got infrastructure already buried in the ground.

The heap leach story

Here's the specific work: 212 production and monitoring wells across the heap leach area, installed as part of a direct injection leaching strategy. The initial production zone has access to roughly 1.7 million tonnes of material, which at projected recovery rates gets you six to eight months of feed.

Actually, that's not quite right. The early data was "encouraging," which is mining-speak for "it didn't blow up and it moved in the right direction." The flow rates came in line with what Cyprium had pencilled in, which keeps the whole machine on schedule.

That's exactly what Cyprium's exploring. Expand beyond 6,000 tonnes. Push towards 20,000 tonnes if the feed sources pan out.

The plant side

Mechanical refurbishment of the solvent extraction plant was substantially complete by the end of September. Piping, pumps, tanks installed and tested. Motors underway on commissioning. You need reagents to actually move solution, but the shell was ready.

The electrowinning plant sat about 80 percent mechanically complete, with anode installation running parallel to refurbishment of the circulation system and cathode handling kit. High-voltage infrastructure got its wiring between the power plant and SX-EW area, though one existing component failed during testing and needed replacing. That's not a catastrophe—it's the sort of thing you find when you actually energise a system that's been sitting idle for decades. Cyprium worked around it using auxiliary power.

By the time the quarter closed, the rectiformer had been installed and was moving towards energisation.

That burn rate's front-loaded, though. They committed A$28.8 million to property, plant and equipment at Nifty alone. Exploration ate A$1.4 million.

To keep the project ticking, Cyprium announced a post-quarter funding package worth up to A$83 million. A$21 million placement, A$5 million Share Purchase Plan, and a proposed US$40 million extension to their existing senior secured debt facility. The capital's earmarked for the open-pit feasibility study, expansion work on SX-EW capacity beyond 20,000 tonnes, and enabling infrastructure.

That's the machinery humming along because the first cathode is only a checkpoint.

Source: "Cyprium is targeting first copper cathode production during Q4 CY2026, during the wet commissioning and ramp-up phase" — Discovery Alert